Rodol Capital Progress Posted by on January 2, 2023 progress reports 0 Comments Rodol capital construction progress report done on december 2022. The specific tasks we have completed: Excavation 100% complete Blinding for all bases Steel cutting, bending, fixing for all the bases Concrete casting for 7 of 13 bases we are working on the following tasks: – Steel cutting,bending,fixing for the retaining wall and basement slab Preparation of formwork for the retaining wall and basement slab Colums up to the ground slab Excavation 100% Blinding 100% Steel cutting, bending, fixing for all the bases 100% Concrete casting 60%